The following fee schedule is herein adopted and made effective July 1, 2017:
(A)
General. Building permit fees shall be as follows:
Total Valuation Fee
$1,000 and less No fee, unless inspection required in which case a $23 fee for each inspection shall be required $1,000 to $50,000 $23 for the first $1,000 plus $6.33 for each additional thousand or fraction thereof, to and including $50,000 $50,000 to $100,000 $333.17 for the first $50,000 plus $5.06 for each additional thousand or fraction thereof, to and including $100,000 $100,000 to $500,000 $586.17 for the first $100,000 plus $3.80 for each additional thousand or fraction thereof, to and including $500,000 $500,000 and up $2,106.17 for the first $500,000 plus $2.53 for each additional thousand or fraction thereof (B)
Special fees are as follows:
(1)
Moving: One hundred fifteen dollars ($115.00);
(2)
Demolition: Fifty seven dollars and fifty cents ($57.50);
(3)
Plan-checking fees: If deemed necessary by the Building official, a review by a designated South Carolina registered architect or engineer of plans may be required. The cost of the review shall be paid by the permit applicant or appellant in board appeals;
(4)
Permit transfer: Fifty seven dollars and fifty cents ($57.50);
(5)
Permit refunds: All except for fifty seven dollars and fifty cents ($57.50);
(6)
Reinspection: Fifty seven dollars and fifty cents ($57.50). For each successive re-inspection, the fee shall increase by twenty eight dollars and seventy five cents ($28.75) accordingly;
(7)
Safety inspection requests: Twenty eight dollars and seventy five cents ($28.75) per hour/fraction;
(8)
Police escorts through PD: Forty six dollars ($46.00) per officer per hour/fraction.
(C)
Zoning fees:
(1)
Approval: Twenty eight dollars and seventy five ($28.75);
(2)
Temporary sign permit: Twenty three dollars ($23.00);
(3)
Containers: Fifty seven dollars and fifty cents ($57.50) for any number of containers permitted at the same time or fifty seven dollars and fifty cents ($57.50) for each container permitted separately.
(D)
Appeals (nonrefundable):
(1)
Board of Zoning Appeals: One hundred seventy-two dollars and fifty cents ($172.50) for the first variance request plus fifty-seven dollars and fifty cents ($57.50) for each additional variance request with a maximum fee of three hundred forty five-dollars ($345.00) i.e., one setback variance request would be one hundred seventy-two dollars and fifty cents ($172.50); two (2) setback variance requests would be two hundred thirty dollars ($230.00);
(2)
Zoning map change: One hundred seventy-two dollars and fifty cents ($172.50);
(3)
Zoning text change: One hundred seventy-two dollars and fifty cents ($172.50);
(4)
Building Board of Appeal: One hundred seventy-two dollars and fifty cents ($172.50).
(Ord. 2005-02, § 2, passed 1-3-05; Ord. 2016-29 , § 1, passed 9-6-16; Ord. 2017-39 , passed 7-10-17)